To assist GeoSea with the installation of jackets for the Moray East Offshore Wind Farm, TWD designed the jacket seafastening and assessed the structural integrity of the jackets during transport.
Seafastening structures were provided to support the jackets in several stages of the project, spanning from the fabrication yard in Dubai, SPMT and inland barge transport, to port storage in the UK where they await installation. TWD also designed grillages with the purpose of them being partially re-used for the multiple voyages for each vessel.
In total 48 jackets have been transported on 3 different vessels, of which 3 are Offshore Substation Platform (OSP) jackets.
Project highlights
As the global wind energy sector expands, a shortage of vessels for handling bigger monopiles is foreseen. Simply scaling up isn’t enough. Download our Whitepaper to explore how TWD tackles supply chain bottlenecks with innovative installation methods, or get our Offshore Wind Track Record to see how we have helped industry leaders succeed in their installations.