Foundation installation pre-piling template for the jack-up barge Goliath

TWD designed a piling template for DEME’s jack-up barge, Goliath. Suspended by winches and guided by the jack-up legs, this template can be easily lowered to the seabed and leveled during pile driving. To safely install the piles within the tight tolerances, the template contains a simple and robust mechanism that has been put in the sleeves. Because the mechanism can be hydraulically retracted, it allows the template to easily retrieve. The template is then lifted against the hull allowing the barge to easily sail to its next location.

 

Project highlights

  • The template assures accurate positioning of the piles throughout the entire piling campaign
  • Due to a smart and effective mechanical design, the template never gets stuck, works fast and accurately
  • Due to its simplicity, fabrication is cost-effective