Precise installation of the lower boat landings through the splash zone
DEME installed 54 wind turbine foundations at the Nordsee One offshore wind farm in the German North Sea, using their jack-up vessel, Innovation. To help with the installation, TWD designed and provided fabrication supervision for various seafastening structures.
One of the most challenging features of this project was the installation of the lower boat landings. To ensure precise positioning of the boat landing through the splashzone without damaging the coating, TWD designed a boat landing installation aid (BIA). The BIA enabled the crew to perform a complex lift and remotely install the lower boat landings. This led to a quick, safe, and efficient installation of Nordsee One (332 MW), which currently gives 400.000 households access to green energy.
Project highlights
As the global wind energy sector expands, a shortage of vessels for handling bigger monopiles is foreseen. Simply scaling up isn’t enough. Download our Whitepaper to explore how TWD tackles supply chain bottlenecks with innovative installation methods, or get our Offshore Wind Track Record to see how we have helped industry leaders succeed in their installations.